The project budget charts and reports compares the total project budget and time with what is already spent. In order to create the report:



  1. Go to the Project Detail and then input the Project Budget and Time

  2. In the Rates screen enter the employee rate


When you run the reports, it will then multiply the rate with the approved time and then compare with the total budget.

SK Dutta,
Architect OfficeClip LLC,
Web-based Business Software,
Ph: +1-770-448-7375,
Web: https://www.officeclip.com

Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.